  5. Installation of electrical-automatic equipment for two pumping stations

Installation of electrical-automatic equipment for two pumping stations

Client: Okseta UAB

Object: Petrašiūnai power plant and Pergalės boiler house owned by Kauno Energija

Year: 2024-2025

Scope of works:

Reconstruction of the Petrašiūnai power plant pumping station consisted of:

  • Dismantling of redundant E/A panels, electrical equipment and cables;
  • Installation of modern electrical-automation equipment;
  • Connection of new equipment into a single SCADA process control and visualization system;
  • Cold commissioning works.

The reconstruction of the Pergalė boiler house’s electrical switchgear and the installation of a new generator was carried out in three phases:

  • Installation of two pumps, cables, cable structures and frequency converters;
  • Control system upgrade and programming of the Automatic Standby Unit (ASU);\
  • Programming of the ASU;
  • Connection of the generator and new electrical section.